There are three key sources of design standards for lifts in office buildings:
- British Standard 5655 part 6.
- CIBSE Guide D.
- Transportation Systems in Buildings and British Council for Offices (BCO) best practice guide.
The criteria for design includes:
- Morning up-peak handling capacity.
- Occupation density.
- Average interval.
- Car occupancy.
- A staircase allowance.
[edit] Morning up-peak handling capacity
Morning up-peak handling capacity is expressed as a percentage of the building’s designed population that needs to be moved in a five minute period. Historically, the general consensus estimated this at 15%. However, the increasing use of flexible hours has reduced mass arrival numbers and the introduction of sophisticated computer controls systems suggest that the 15% figure might be radically reduced.
A 2004 morning peak survey of nine West End and City of London office buildings by Stanhope (Lift performance and specification) concluded 6% of an assumed population using 14m2/person recorded actual reality. Furthermore the survey concluded that lunchtime patterns were more relevant as lifts are being utilised in both directions as people enter and leave the building simultaneously. The Stanhope survey suggested 7% is an adequate design capacity figure.
[edit] Occupation density
Occupation density should include a 15% allowance for absenteeism. Multiple tenancies occupy space more densely than single tenants and trading floors have particularly dense spatial requirements. 10m2 per person is a very conservative figure that matches British Standards. BCO however believe 14m2 to be more realistic for standard offices. NAO audits carried out in 1999 on public sector buildings suggested 19m2 per person was a realistic density figure.
[edit] Average interval time
Average interval time is the theoretical time for a single lift to complete the cycle of receiving passengers on the ground floor, discharging them on the various upper floors and returning to the ground floor. Where there are banks of lifts, the average interval time is divided by the number of lifts in the group. These calculations are based on averages and not the upper limit. 20 to 30 seconds provides a range from standard to prestige.
Waiting times are not the same as average interval times:
- 75% car loading of a 30 second average interval time equals 22.5 seconds waiting time.
- 85% car loading of a 30 second average interval time equals 25.5 second waiting time.
It is waiting times that are the driver of public perception and are of interest to letting agents.
[edit] Car occupancy
Car occupancy is 20% less than the stated capacity. A 16 person car in practice will carry 13 people.
[edit] Staircase allowance
A staircase allowance is suggested by CIBSE, with 50% first floor occupants preferring to use the staircase if in close proximity to a lift.
[edit] Conclusion
Standards and criteria established in the mid-seventies are open to challenge. The Stanhope survey suggested that updated criteria might result in the following:
- Occupation density: 14m2 per person (nett lettable area).
- Lunchtime loading:
- 5% down, 3% up 12:00 to 12:40 per 5 mins.
- 3% down, 3% up 12:40 to 13:20 per 5 mins.
- 3% down, 5% up 13:20 to 14:00 per 5 mins.
- Capacity factor: 60% of car rating.
- Average waiting time: 25 secs lunchtime.
- Inter-floor traffic: 1% of design population 12:00 to 14:00 hrs.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- British Council for Offices.
- Criteria for the choice of a structural system to be included in office specification.
- Lifting platform.
- Lift motor room.
- Lift Standards: EN 81-20 and EN 81-50.
- Lifts.
- Lifts and Escalators: A Quality Perspective.
- Lift shaft.
- Office definition.
- Office space planning.
- Post Occupancy Evaluation: operational performance of a refurbished office building.
- Stairs.
- Structural systems for offices.
- The importance of service lifts.
- The science of lifts.
- The world's fastest lifts.
[edit] External references
- Stanhope position paper – Lift performance and specification published February 2004
Featured articles and news
Resident engagement as the key to successful retrofits
Retrofit is about people, not just buildings, from early starts to beyond handover.
What they are, how they work and why they are popular in many countries.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.